| Sl. No. |
RFP Clause |
|
| 1. |
Page No 32 - Para 9.e –Payment Terms |
Along with the existing clause following line is added:
“One Time Installation charges will be paid after successful commissioning and acceptance” |
| 2. |
Page No 27 – Para 8.b – Minimum Eligibility Criteria |
The following line is changed and can be read as: